Development Review Timelines

Planning Department Development Application Review Timelines
Review Process Schedule 1 Schedule 2 Schedule 3

Minor Site Plan
Amendments,
Conditional Use
Approvals; CMRS
tower Site Plans;
Sign Variances
Site Plans and
amendments;
Redevelopment
Plans; Plats;
Street Vacations
& Zonings
Zoning under 50
acres in
conjunction with
any categories 1
or 2 application
types, Master Plans
& FDPs
1st City Review 15 days 15 days 15 days
Application 2nd Submission
15 days 15 days
2nd City Review
15 days 15 days
Application 3rd Submission

10 days
Applicant Amended Submission* 5 days 5 days 5 days
Other Processing Tasks 12 days 12 days 12 days
3rd City Review

15 days
Total working days 32 days 62 days 87 days
Total weeks 6.5 weeks 12.5 weeks 17.5 weeks

*Used when minor corrections are needed.
 

Civil Construction Plan Review Timelines
Civil Construction Plans Up to 39 sheets 40-59 sheets 60-79 **sheets
1st City Review 15 days 20 days 25 days
Consultant Revisions on 1st Round 5 days 5 days 5 days
2nd City Review 10 days 15 days 20 days
Consultant Revisions on 2nd Round 5 days 5 days 5 days
Final City Reviewand Approval 5 days 10 days 10 days
Total working days 40 days 55 days 65 days
Total weeks 8 weeks 11 weeks 13 weeks

**Plan sets of 80+ sheets, please contact Engineering Services Division for schedule.
 

Building Plan Review Timelines
Building Plan Review Tenant Finish Limited Sing Family
Residential
Commercial
& Multi-Family
City Review for Code Compliance 3 days 7 days 21 days 26 days
Code Corrections by Applicant 7 days 5 days 7 days 12 days
City Review of Code Corrections 1 day 2 days 2 days 2 days
Total working days 11 days 14days 30 days 40 days
Total weeks 2+ weeks 2+ weeks 6 weeks 8 weeks

Note:  Building Permits cannot be issued until all other Development Review processes have been completed.
 

Irrigation Construction Plan Review Timelines
Irrigation Construction Plans Up to 5 sheets Up to 10 sheets 11 + Sheets
1st City Review 10 days 15 days 20 days
Consultant Revisions on 1st Round 5 days 5 days 5 days
2nd City Review 10 days 10 days 10 days
Consultant Revisions on 2nd Round 5 days 5 days 5 days
3rd City Review 5 days 5 days 5 days
Total working days 35 days 40 days 45 days
Total weeks 7 weeks 8 weeks 9 weeks

This is an approximate timeline that may vary due to plan quality and number of plans under review.